Gusabad (Kusapat, Կուսապատ) is one of the historical villages of Artsakh, located in the Mardakert region of the Artsakh Republic, 11 km south-west of the regional center. The elevation is 776 m (2,546 ft). The village has 60 houses, 280 inhabitants, of which 40 are schoolchildren and 30 are preschoolers. Mainly Armenians, and some Greeks. The people of Gusabad are mainly engaged in cattle breeding and gardening. Gusabad is one of the oldest villages in Artsakh, founded in the 15th century by an Armenian Prince Atabek III Jraberdtsi. In 1992, the Azeris seized the village and destroyed it. About a year later, the village was liberated.
FOA funded and completed many projects in Gusabad in many phases. See the project list and pictures below. THE TOTAL COST IS $180,001.
Project #192; Cost $1,500: In 2022, FOA purchased 3 new computers for the Karian School. The cost was funded by Mr. Hayk Zerunian.
********************************************************
The $15,325 funds for the Varujan Karian School Gymnasium’s renovation were from the donations made in lieu of flower for Simon Karian, Verkin Gagosian, and Michael Kazanjian funerals.
The renovated gymnasium will be used for two purposes:
As a sport hall for the school kids as well as regional sport events.
As an assembly hall for local events such as performances, lectures, and community functions.
Project #191; Cost $5,725: In 2022, FOA funded for the ceiling encapsulation of the Varujan Karian School’s Gymnasium.
Project #190; Cost $6,200: In 2022, FOA funded for the replacement of the floor of the Varujan Karian School’s Gymnasium.
Project #183; Cost $3,400: In 2021, FOA funded for the replacement of windows and doors of the Varujan Karian School’s Gymnasium.
********************************************************
Project #182; Cost $1,400: In 2021, FOA funded for building a new concrete table with seats in the Varujan Karian Memorial fountain.
Project #95; Cost $2,200: In 2017, FOA funded for building a new concrete floor in the Varujan Karian Memorial fountain.
Project #94; Cost $500: In 2017, a Memorial Stone was erected at the Varujan Karian Memorial Fountain to engrave the names of deceased FOA organizing committee members. Then the second stone was added later in 2018.
Project #10; Cost $33,000: In 2001, Varujan Karian School was renovated with new water pipes, toilets, light fixtures, Stoves, and other miscellaneous repairs.
Project #4; Cost $118,876: In 1995, Varujan Karian School was Constructed in his memory. The cost does not include additional donated material sent from Los Angeles.
Project #3; Cost $7,200: In 1994, Varujan Karian Memorial Fountain was built. From 1995 to 2015, several small projects were implemented to sustain the structure.
ՅՈՒՇԱՂԲԻՒՐԻ ՊԱՏՄՈՒԹԻՒՆԸ (հայերեն)
Varujan Karian Memorial Fountain Construction in 1994,
and other projects #3, #94, #95, #182 from 1994 to 2022.
Total cost $11,300
Varujan Karian School construction in 1995,
and other projects #4, #10, #183, #190, #191, #192 from 2001 to 2022. Total cost $168,701
Project #192: Purchase of 3 new computers cost $1,500 in 2022
in 2021 & 2022: Gymnasium’s pictures before, during, and after project completions. Total Cost $15,325.
Project #191: In 2022, ceiling encapsulation Cost $5,725.
Project #190: In 2022, floor replacement Cost $6,200.
PROJECT #183: In 2021, GYMNASIUM’S WINDOWS & DOORS REPLACEMENT COST $3,400.
Thank you letter from the school principle
Project #4: Varujan Karian School construction
Cost $118,876 in 1995
Project #10: New bathrooms at Varujan Karian School in 2001